Within Invantive Estate you can specify a phasing for projects. Each project is then always in one of the possible project phases.
Furthermore, you can specify whether each project phase is possible for every product group, or only for specific product groups. Finally, you can set up a logic for the sequential project phases a project goes through. This is very similar to the workflow of a process within Invantive Estate.
In this example, I’ll use a Land Development product group to show how you can restrict the list of possible project phases and the transitions between these project phases.
Project Phases for Land Development
A list of possible project phases within Land Development could be:
- G_H: Feasibility Study;
- G_E: Land Development;
- AF: Completed.
Each land development project is therefore in either the “Feasibility Study” phase, the “Land Development” phase, or the “Completed” phase.
Project Phase Transitions
With the help of project phase transitions, you can set up that not every arbitrary transition can be made between project phases. For example, as follows:
- From “Nothing” to “Feasibility Study”: the feasibility can start being studied.
- From “Feasibility Study” to “Land Development”: the land can start being developed.
- From “Land Development” to “Completed”: the land development project has been completed.
In Invantive Estate, this looks as follows in the “Project Phase Transitions” screen:
Note that a way back from “Land Development” to “Feasibility Study” has also been defined. This is used to move a project’s phase back a step.
If you want to change the phase of a land development project in the “Projects” screen, you’ll only see the project phases that are possible based on the current phase. This applies regardless of whether you’re using the integration in Microsoft Outlook or the web user interface.